Project Timeline

January – June 2021

Site Surveys
Onsite surveys and investigations such as noise monitoring, topographical surveys, ecological assessments and ground investigations, to understand constraints and inform our initial plans for the site.

January – June 2021
February – April 2021

Early Stakeholder Engagement
Engagement with key stakeholders to provide local knowledge and insight to help shape our initial thoughts for the Friar Park site.

February – April 2021
10th May – 20th June 2021

Phase 1 Consultation
Six-week consultation to present first thoughts and masterplan options. Providing people an opportunity to:

  • review what has been presented;
  • ask questions about the information; and
  • provide feedback to inform further development of the plans.
10th May – 20th June 2021
June 2021 – October 2022

Development of our plans following review and consideration of stakeholder feedback and ongoing site investigations. 

June 2021 – October 2022
7th November – 19th December 2022

Phase 2 Consultation
Six-week consultation to present preferred masterplan. Providing people the opportunity to:

  • view how their feedback has informed the development of the plans; and 
  • provide final comments ahead of finalising the proposals.
7th November – 19th December 2022
25th November 2022

Drop-in public information day 12-4pm
Friar Park Millennium Centre, Friar Park Road, Wednesbury WS10 0JS

25th November 2022
26th November 2022

Drop-in public information day 10-2pm
Friar Park Millennium Centre, Friar Park Road, Wednesbury WS10 0JS

26th November 2022
Feb 2023

Finalisation of the masterplan.

Feb 2023
From April 2023

Discussions commence with potential Developer Partner.

From April 2023